Our core competencies as a prime sub with self-perform capabilities are: GWB system installation, ACT system installation, doors and hardware installation, solid surface prefab installation, demolition, concrete, millwork, rough and finish carpentry. F&P short term and long terms goals include continuing to grow our relationships as a prime contractor (junior partner on JV projects), self-perform general contractor of interior finishes, and subcontractor of interior finishes in alignment with the needs of our clients, partners, and community.

Hospitality

Meyerson Symphony Hall

Dallas

  • Remove, refurbish and reinstall 1600 seats, including bottoms and bucket hardware
  • 4-6 weeks, $100,000 (approx.)
  • Completed on time and within budget during a short break in the concert schedule

One Main Place/Westin

Dallas

  • Framing, drywall, flooring and ceiling tile installation and miscellaneous scope gaps
  • 20,000+ SF, 3-6 months, $200,000+ (approx.)
  • Resolved all scope gap challenges to complete project on time and within budget

Healthcare

Parkland Hospital

Dallas

  • Minor demo, install doors and hardware, plus GWB and ACT systems
  • 30,000 SF, 6-8 weeks, $207,000 (approx.)
  • Completed on schedule and within budget

Children’s Medical Center

Plano

  • Demo; GWB, ACT systems and rolled flooring installation in ER and Clean Room
  • 10,000 SF, multiple locations over 6 months, $200,000+ (approx.)
  • Achieved all schedule and cost objectives while working in occupied hospital spaces with aggressive targets

Horizon Medical Center

McKinney

  • Onsite supervision, excavation and concrete work
  • 40,000 SF, 12-16 weeks, $50,000 (approx.)
  • Successfully managed subcontractor performance and obtaining CO to completion

Stephen A. Cohen Veterans Clinic

Farmers Branch

  • Complete finish-out of existing tenant space, including light demo
  • 10,000 SF, 6-8 weeks, $475,000 (approx.)
  • Completed on schedule and within budget

Nighthawk Pediatric Health Clinics

Dallas

  • Complete renovation and finish-out of existing shell building
  • 15,000 SF, 8-12 weeks, $560,000 (approx.)
  • Completed on schedule and within budget

K-12

Arlington Heights

Fort Worth ISD

  • Combination of renovation and new construction of early college high school
  • 175,000 SF, 18 months, $40M (approx.)
  • Completed on schedule and within budget

Bezos Academy

East Dallas

  • Complete tenant finish-out of four existing buildings
  • 30,000 SF, 18 months, $2M (approx.)
  • Completed on schedule and within budget

Bedford Law Academy

Dallas ISD

  • New construction of state-of-the art law academy
  • 180,000 SF, 20 months, $70M (approx.)
  • Project currently in progress

Higher Education

UNT: Frisco Mill Park

Frisco

  • Demo, paint, installation of GWB and ACT systems
  • 10,000 SF, three week turnaround, $40,000 (approx.)
  • Completed on schedule and within budget

UNT: Inspire Park

Denton

  • Demo, paint, installation of GWB and ACT systems
  • 10,000+ SF, 4-6 week turnaround, $50,000 (approx.)
  • Completed on schedule and within budget

UNT: Office of Advancement

Denton

  • Interior renovation project
  • Varied tasks throughout several areas of the building
  • All completed on time and within budget as one package

UNT: Main

Denton

  • Installation of GWB and ACT systems, storm drain, canopy and flooring; repairs on maintenance issues
  • 10,000 SF, work over several months at different times, $100,000 (approx.)
  • Completed on schedule and within budget

UNT: Denton Campus

Denton

  • Work on multiple buildings and locations, including installation of GWB and ACT systems, paint, flooring, landscaping and power washing
  • 100,000+ SF, tasks scheduled over several weeks/months
  • Completed all on schedule and within budget

Dallas College

Dallas

  • Projects on multiple campuses, including service roads, electronic gate installation, installation of GWB and ACT systems, carpet, painting, grading and landscaping
  • 100,000+ SF, 2-3 years, $4M (approx.)
  • Completed all on schedule and within budget

Multifamily

Marado

Plano

  • Luxury rental community with 183 units, 12,700 SF of restaurant and retail space, and 335 parking spaces in an underground garage
  • Podium style base with wood framed structure above, plus an elevated pool
  • Work included framing and rocking the under-podium areas, and project involved a partnership with the City of Plano; $1.0 M

Nove at Knox

Dallas (Knox St)

  • Nineteen floor luxury multifamily project in Dallas’ Knox-Henderson district, with 310 rental units, 24 penthouses and exceptional views
  • Poured in place structure with masonry and punch opening skin; four elevators, elevated pool, four-story parking garage and large amenities deck
  • Work included specialty concrete and temporary safety services; $200k

Graco

Plano

  • Subcontracting services on a four building, 4/5 story wood frame wrapped multifamily complex
  • Project included 270 residential units, a 320-car precast parking garage, and first floor retail on an urban/downtown site
  • Work performed included site demolition and grading, as well as concrete paving and hardscaping; $1.0M

Transportation

TXDOT/Hopkins County Safety Rest Stop

Hopkins County

  • Subcontracting services encompassed four main buildings and ten site structures, including canopies, arbors and pedestrian bridges
  • Also involved cold form framing, wallboard, acoustical ceilings, cedar siding, joint compounds, paint and epoxy coatings
  • 120 acre site; $700k contract value

DFW Airport/Hyatt Hotel

Dallas

  • Safely build a high quality sloped metal access roof platform in an active, secure airport environment
  • 15,000 SF of sloped roof, 4-6 weeks, $247,000 (approx.)
  • Successfully navigated many complexities and challenges to complete work on schedule and within budget